Overview
The Wuling G200P BIW project is a contract-level reference for a passenger-vehicle body welding line in China. DUOYUAN's published case now records the station-code boundary from MB010 to FL180, 10 welding units, 6 controllers, 7 terminal packages, and a confirmed annual capacity of 60,000 units. The scope was not limited to a single welding fixture. It covered the main welding line, adjustment line, mechanical conveyor line, upper-body manual line, side-frame manual line, and the related steel-structure design, manufacturing, installation, and acceptance work. For buyers comparing BIW suppliers, this is useful because it shows the real project boundary behind a turnkey body-shop offer.
Challenge
The buyer needed a body-shop package that could organize a complete G200P BIW flow instead of a loose list of welding fixtures. The line had to connect station-code planning, manual body sections, mechanical transfer, control packages, and final acceptance into one delivery boundary.
Solution
DUOYUAN organized the body-shop package around main-line welding, adjustment, mechanical conveyor transfer, upper-body manual work, side-frame manual work, fixture support, opengate flexible switching, lifting roller beds, AGV shuttle, automatic gluing, visual guidance, controls, and acceptance evidence.
Delivery
The delivery scope was structured as a turnkey BIW project. DUOYUAN tied equipment design, manufacturing, installation, commissioning, and final acceptance into a three-month project window, while keeping the station-code list and package counts visible for scope comparison.
Result
The contract record supports three citable facts: the G200P BIW line covered station codes MB010-FL180; the delivery included 10 welding units, 6 controllers, and 7 terminal packages; and the project was planned for 60,000 units per year with final acceptance in a three-month window.